Six people to can perform a task in 8 days. If we add 2 equally able people, how long would it take?

Respuesta :

madankapoor10
madankapoor10 madankapoor10
  • 24-03-2014
1 man does 1/48th piece of work per day
then 8 man do 1/6th piece of work per day
so they can do the work in 6 days

Answer Link
salmheiri
salmheiri salmheiri
  • 21-02-2022

Answer:

6 days

Step-by-step explanation:

Answer Link

Otras preguntas

suppose someone's pores were blocked and sweat could not escape. what would happen
SImplify Each Expression ~~~~~~~~~~~~~~~~~~ 6x+(5x-8) -(2-x)-3(6+8x)-12 11-(3x-6)+2(4x+5)-x (x+2)-(x-2)-12x ~~~~~~~~~~~~~~~~~~~ -Please show work-
What Are The Main Complaints And Demand Of The People In The Non Democratic Country?
changes to the earth that can be explained by plate tectonics include all the following except ___ Earthquakes,erosion,mountain ranges, volcanoes
What are the values of x in the equation x(x-6)=4(x+6)
Find the roots of the following equations. a) 4x+9=34 b) (x-4)(x+2)=0 c) 2x^2-6x+4=0
Why were the members of the Third Estate dissatisfied with their way of life under the Old Regime?
what does standard deviation mean?
The sum of a number and twice the second number is 24. Determine the two numbers to maximize their product. Show your work (equations, calculations, etc.) If
which of the following statements if true of the gulf of Tonkin affair