Project X and project Y have the same number of activities (500 activities each). Project X has 25 critical paths and project Y has 3 critical paths through the network. As a result, project X has several more activities in the critical paths than that of project Y. Which project will most likely be harder to manage (i.e., completing the project on-time by the due date) for the project manager