Crane Construction Company had a contract starting April 2021, to construct a $22800000 building that is expected to be completed in September 2023, at an estimated cost of $20800000. At the end of 2021, the costs to date were $7072000 and the estimated total costs to complete had not changed. The progress billings during 2021 were $3600000 and the cash collected during 2021 was 3080000. Crane uses the percentage-of-completion method. For the year ended December 31, 2021, Crane would recognize gross profit on the building of:____.a. $680000. b. $0. c. $13728000. d. $620351.