30 workers can complete a work in 40 days in how many days would 20 men complete the construction​

Respuesta :

s1m1
s1m1 s1m1
  • 25-11-2020

Answer:

27

Step-by-step explanation:

(30 workers/40 days) = (20 workers/x days) cross multiply

30*x=40*20 divide by 30 both sides

x= 800/30

x≈26.67

So they will need 27 days

Answer Link

Otras preguntas

the chef has 50 pounds of strip lion. the trim loss on the strip lion is 60% and the cooking loss is 20% of the trimmed weight. how many pounds of trimmed, cook
can somebody help please?? urgently
chemist is using 387 mL of solution of acid in water if 13.3 of the solution is acid how many milliliters of acid are there round answer to nearest tenth
What simplified ratio correctly compares 24 months to 3 years? Drag and drop the appropriate numbers into the boxes. :
What is the closest circumference of a well
What is 1,305 divided by 12
what else can I add in my concluding paragraph? here is what i have so far. All allusions represented in the situations presented help encourage suggestions an
Consider randomly selecting a student at a large university. Let A be the event that the selected student has a Visa card, let B be the analogous event for Mast
A meteorologist was accurate 90% of the time, reporting accurately for 45 days. How many days of weather did he report
Need helpppp!!!!!!!!