a field can be cleared by 33 men in 15days. how many more person required if the field has to be cleared 4 days earlier?​

Respuesta :

wsookhuei
wsookhuei wsookhuei
  • 24-10-2020

Answer:

12 men

Step-by-step explanation:

33men x 15 days = the whole project

Let the men that are required be x.

33 x 15 = (15-4)x

495 = 11x

x = 45

Answer Link

Otras preguntas

Geometry  The diagonals of a  kite are in the ratio of 3:2. The area of the kite is 27 cm^2 .  Find the length of both diagonals. (Hint: Let the lengths of the
Which of the following tends to form a cation (positive ion) with a charge of 2+? a. Na b. O c. He d. Mg
How many moles of sodium hydroxide are produced when 1.00 mol sodium peroxide reacts with water
it's generally recommended that athletes consume approximately____ percent of their daily calories?
what word best describe chlorophyll
What reasons does Palmer give to justify the arrest of communists in the United States?
who was not free in medieval England
Balance the equation : ...NO2 + ...O2 + ...H2O = ...HNO3
How are boundaries between river systems and natural vegetation regions different?
Seb made a jump of two and a half meters Kirsty's jump was 10 centimeters longer how long was Kirsty's jump