30men can finish 1/7of a work in 2days.18men will do othe remaining work in ?

Respuesta :

chumxo chumxo
  • 24-09-2016
7/7-1/7=6/7 is the rest of work
1/7 work takes 2days
6*1/7=6/7 work takes 6*2days=12days
30 men takes 12 days to finish the rest of work (6/7)
18 men takes 18*12/30= 7.2days
Answer Link

Otras preguntas

In “The Scarlet lbis,” why does the narrator rename his little brother Doodle ?
(01.02 MC) Each week, Abigail earns $75 for every shift she works at the pizzeria and $25 for every dog-walking job. She uses the expression 75x + 25y to keep t
What do you know regarding ischemia that is confined to only the posterior and or lateral segments of the left ventricle?
Marine magnetic anomalies can be used to estimate the
anyone wants to help?
Review questions discuss one of the common myths of becoming a parent and why it is not true. what are the qualities of a nurturing parent? there is more than o
Eloise is investing in a retirement account. She plans on adding an additional $50 at the end of every year and the expected monthly rate of return is 3% of the
For every increase of one on the Richter scale, an earthquake is ten times more powerful. Which of the following models this situation? A.linear function with
A university student who is enrolled in school full time and not seeking employment is considered:
During World War I many American women help gain support for the suffrage movement by A) protesting against the war B) joining the military service C)working i