seven people need 90 days to repair and paint a heritage building.if the job should be completed in 15 days.how many more people need to be employed.​

Respuesta :

khababnazir10
khababnazir10 khababnazir10
  • 22-11-2019

Answer:

Here is your answer mate

Step-by-step explanation:

As we know that 7 person take 90 days so 1 person takes 90×7=630 days

As work has to be finished in 15 days than 630/15=42 so

42 people can complete work in 15 days but as we have already 7 people employed so required are

42-7=35 so 35 more are needed

Answer Link

Otras preguntas

A football players parents spent $119 on tickets for friends to attend the game. Tickets were $7 and $10 and they bought an equal number of both kinds. How many
Which is more important: sleep or food?
Does the table describe x as a function of y?
work out the equation of the line which has a gradient of 3 and passed through the point (-1,3) please help, thank you.
What is the relationship between the ideal gas constant R and the Boltzmann constant k?
Determine the molecular formulae of the following compounds; a) Magnesium oxide b) Lithium carbonate c) Copper (11) nitrate
to find the slope of a line can you choose any two points on the line?
the mean weight of 60 students of a class is 40 kg the mean weight of boys is 50 kg while that of the girls is 30 kg find the number of boys and girls in the sc
a cellphone company charges $49.99 per month plus 10 cents for texting. write and solve an equation to determine how many texts were used in a month if the mont
Evaluate. 1 1/3+2 2/5 A)3 3/8 B) 3 11/30 C)2 11/15 D)3 11/15