The critical path on a project can change as the project progresses. select one:

a. true

b. false

Respuesta :

mirrorkitten
mirrorkitten mirrorkitten
  • 02-04-2019

The answer is True.

In project management, critical path refers to a sequence of stages that would require the smallest amount of time possible to bring a project to completion.

Critical path can change during a project since there might be circumstances during it which would lead certain activities to be finished longer or faster. Critical path can be determined by a specialized algorithm technique.

Answer Link

Otras preguntas

Write the quadratic equation whose roots are-1 and 6, and whose leading coefficient is 4 (Use the letter to represent the variable.)?=0
what 3 numbers multiply to get 63?
For which system of equations is (2, 2) a solution? A.–3x + 3y = 0x + 6y = 10B.–2x + 5y = –64x – 2y = 4C.5x – 2y = –63x – 4y = 2D.2x + 3y = 104x + 5y = 18
Solve this.. ➕+ ➕ + ➕+ ➕=30 Fill the boxes using (1, 3, 5, 7, 9, 11, 13, 15) U can also repeat the numbers..
What was good abt technology in 1930
What polynomial when divided by 2y^5 yields 4y^2-2y+9 as a quotient?
find the zeros of y=x²-1 from a graph.
1. (k+7)² =2892. (2s-1)² =2253. (x-4)² =169please help me answer these :)
in the given figure , if PQ ll RS , angle TRS = 105 and angle RTP = 30 , then the value of x is
16. The spreading of sound waves around openings in barriers is called A. reverberation. B. an echo. C. diffraction. D. refraction.