A project management plan is the main output of the project ________ knowledge area.

Respuesta :

ariston ariston
  • 21-08-2018

A project management plan is the main output of the project Integration management knowledge area

Explanation: The Project integration management which is the first of the 10 PMBOK knowledge areas involves developing a project charter and project management plan

Answer Link

Otras preguntas

Which sentence describes the rising action of the story
Find the surface area
Heterozygote advantage should be most closely linked to which of the following? A) sexual selectionB) stabilizing selectionC) random selectionD) directional sel
#10 What is the adverb tomorrow modifying?
Please Help!!!!!!! Given that f(x) = 4x +1 and g(x) = x^2 -2, which of the following is an expression for f(g(x))? a. 16x^2 + 8x - 1 b. x^2 + 4x - 1 c. 5x^2 -
I need translations and plural versions
List parallelograms, polygons, quadrilaterals, and rectangles in order from the least specific group to the most specific one. A) parallelograms, polygons, qu
What is the value of the ratio of the surface area to the volume of the cylinder?
The jacket is on sale for $36 which Is 80% of the original cost. What is the original price of the jacket?
What describes the thematic difference between “to my dear loving husband” and “to the kings most excellent majesty”