Draw the network diagram based on the following information: 1. is the first job of the project. 2. N are the two final jobs for project completion. 3. K precedes O. 4. N follows L and M. 5. J restricts the start of K and M. 6. C and B depend on the completion of A. 7. D follows B and may go on in parallel with C and E. 8. E follows C. 9. I restrict the start of J and L. 10 .H and G also restrict K and M. 11. F must precede G and may go in parallel with H. 12. E and D restrict H and I. 13. C must precede F.