Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 6, and 14 days respectively, compute the PERT expected activity time for this activity.
A) 8
B) 6
C) 7
D) 9
E) None of the above

Respuesta :

Otras preguntas

What are the differences between algea and fungi​
Plsssss help I’m being timed -Also you cannot remove the commas that’s already in their!!!!
A ride at an amusement park moves the riders in a circle at a rate of 6.0 m/s. If the radius of the ride is 9.0 meters, what is the acceleration of the ride?
what is the central idea in the story "The Tardigrade: Practically Invisible, Indestructible, 'Water Bears'"?
12) What action prompted England and France to declare war on Germany in 1939? ASAP
Can someone help me with this?
Select the adverbs. My sister Elizabeth hardly touched her dinner, but afterward she complained of being hungry.​
Basham can hold 80 gallons of water how far is it follows at a rate of 4 gallons per minute what percentage of the child will be filled out
PLEASE HELP ASAP! PLEASE! Write down a list of thing the African Americans helped with
3x - 4y =7 3x - 4y =9